Clark Regional Wastewater District — Standby Power Improvements
Permanent standby power evaluation and implementation for seven wastewater pump stations.
Client
Clark Regional Wastewater District
Location
Clark County, WA
Industry
Wastewater
Project Overview
The Challenge
Clark Regional Wastewater District needed to evaluate and implement permanent standby power improvements at seven of its pump stations. The District required a comprehensive assessment of existing conditions, generator sizing, and a clear path forward for upgrading critical infrastructure to ensure reliable operations during power outages.
Our Approach
The Solution
Industrial Systems completed a two-phase effort to address the District's needs.
**Phase 1** involved verifying conditions, sizing generators, reviewing record drawings, and producing a technical memorandum with recommended approaches and cost estimates.
In **Phase 2**, the District moved forward with finalizing permanent generators and transfer switches at three of the pump stations. IS provided electrical and control system design, verified site conditions, and produced complete drawing packages at the Draft and Final stages. Updated cost opinions, specification editing, and final phase support were also provided.
Results
Project Outcomes
This was one of more than a dozen projects Industrial Systems has completed for Clark Regional Wastewater District over the years. The company has had an on-call agreement with the District since 2006 and was recently awarded a new contract to continue providing services to this long-standing client.
Seven stations assessed for standby power
Pump Stations Evaluated
Permanent generators and transfer switches at three stations
Generators Implemented
On-call agreement since 2006
Client Relationship
Generator sizing, condition assessment, and cost opinions
Feasibility Scope