Project Overview
The Challenge
Industrial Systems was selected as the City of Scappoose's SCADA provider via a qualification-based selection process. The first project completed under this agreement was the recreation of SCADA systems for the City's water treatment plants.
The City operates two WTPs and needed new SCADA systems designed for both to have the same look and feel while maintaining independent systems to provide resiliency.
Our Approach
The Solution
Industrial Systems completed the implementation of a preliminary SCADA system to allow the City to better control their existing wastewater treatment plant while work on the design of their new plant was completed. The SCADA system provides automatic control and remote access for WAS pumping, aeration, and influent pumping. This system was enhanced to include control of the new plant.
The new SCADA system was brought into operation while maintaining full operation with zero downtime. The solution was implemented using state-of-the-art Tridium Control Microsystems PLC, with extensive data logging and trending to aid in tracking application performance, and multiple types of serial and Ethernet communications to board assets.
Results
Project Outcomes
Both water treatment plants now operate under unified SCADA systems with a consistent interface, giving operators a familiar environment across facilities while maintaining independent system resiliency. The City benefits from automatic control, remote access, and comprehensive data logging and trending capabilities.
Two water treatment plants with unified SCADA
Plants Upgraded
Zero — cutover with full operation maintained
Downtime
Tridium Control Microsystems PLC
Platform
Automatic control, remote access, data logging & trending
Capabilities
Project Team
Team Members
The people behind this project.
Related Work
More Water Treatment Projects
Explore similar case studies.
-
Water Treatment | Duvall, WACity of Duvall — SCADA Master Plan & Water System Improvements
SCADA Master Plan development and full system implementation including Wonderware SCADA, PLC-based RTUs, private cellular network, and chlorine monitoring for the City of Duvall's water system.
-
Water Treatment | Stayton, ORCity of Stayton
50% facility expansion with a PLC-5 to ControlLogix migration, fiber optic ring network, and modular Wonderware SCADA programming with reusable control and HMI blocks.
-
Water Treatment | Portland, ORGasco
Complete SCADA system design for a groundwater treatment facility — from initial manual control to fully automated, unattended 24-hour operation with redundant remote access.